Work to reduce the height of Warren Dam's spillway is complete, as part of SA Water's proactive measures to ensure the dam continues to safely operate during major rainfall events.
More than 100 cubic metres of concrete was removed from the spillway crest during the past two months to lower it by around 1.9 metres and create a 20-metre-wide slot to enable water from the reservoir to be released d...